Chief Secy Kundra seeks time-bound action to resolve delays on infra projects across Ladakh

LEH: Chief Secretary Ashish Kundra has directed the Public Works Department (PWD) and other executing agencies to identify the causes of delays in infrastructure projects across Ladakh, work out practical solutions with clear timelines and strengthen coordination to accelerate the completion of pending road and building works.

Chairing a review meeting of the PWD, Kundra assessed the financial and physical progress of ongoing projects and called for a consolidated assessment of major works being executed by the PWD, Border Roads Organisation (BRO), Central Public Works Department (CPWD) and National Highways and Infrastructure Development Corporation Limited (NHIDCL).

Secretary, PWD, Baseer Ul Haq Chaudhary, presented an overview of projects under the State Sector, Central Road and Infrastructure Fund (CRIF), Pradhan Mantri Gram Sadak Yojana (PMGSY) and other development programmes. The review covered Special Development Package works, BRO projects, completed works and implementation bottlenecks.

The Chief Secretary stressed that delays arising from land acquisition, land availability, wildlife clearances, regulatory approvals and other constraints must be clearly identified and addressed through coordinated consultations with executing agencies, Deputy Commissioners and relevant stakeholders. Departments were asked to explain the reasons for delays and propose workable solutions backed by realistic timelines.

He also directed agencies to maintain proper records of completed works, including photographs and district-wise progress reports, to strengthen monitoring and verification. Deputy Commissioners were asked to play a more active role in reviewing projects in their districts and coordinating with executing agencies and user departments.

The meeting also reviewed road connectivity in unconnected villages, maintenance requirements, expenditure and the progress of CRIF-funded and other development works. Kundra stressed that project priorities should reflect public needs, connectivity requirements and available resources, with maintenance liabilities factored into planning.

Building infrastructure for government departments and the newly constituted Hill Development Councils also came up for discussion. The Chief Secretary called for advance planning of office accommodation and essential facilities across districts, ensuring that completed buildings are put to effective use. Integrated tendering, rationalisation of project estimates and delegation of financial and administrative powers were also discussed as measures to improve execution.

The status of medical college infrastructure and the responsibilities of executing agencies were reviewed. The Chief Secretary directed the PWD and other concerned agencies to coordinate on pending works and review progress at a follow-up meeting after ten days. The meeting was attended by Secretary, PWD, Baseer Ul Haq Chaudhary; Officer on Special Duty to the Chief Secretary for Special Projects, Moses Kunzang; Chief Engineer, PWD, Abdul Mutalib; Joint Director, Planning, Tsering Angdus; and other officers and officials.