KARGIL: The under-construction Rs 58-crore Sewage Treatment Plant (STP) at Sher Bagh emerged as the focal point of Chief Secretary of the Union Territory of Ladakh Ashish Kundra’s inspection of development projects across Kargil district on Saturday, with the senior bureaucrat reviewing progress on the civic infrastructure project designed to strengthen the town’s wastewater management system.
Accompanied by Deputy Commissioner Kargil Rakesh Kumar, senior district officials and representatives of executing agencies, Kundra was briefed by officials of the Public Health Engineering (PHE) Department on the status of the STP, which is being developed using NDBR technology.
Officials informed the Chief Secretary that the plant, designed with a treatment capacity of 2 million litres per day (MLD), will cater to wards 10 to 13 within the Kargil Municipal area and provide sewerage treatment facilities to nearly 1,450 households upon completion. The project is expected to strengthen urban sanitation infrastructure and improve wastewater management in the expanding municipal limits.
Reviewing the project on site, Kundra directed the executing agencies to maintain the pace of construction while ensuring adherence to prescribed engineering standards and project timelines.
The Chief Secretary later inspected the 300-metre motorable bridge being constructed between Baroo and Andoo Kurbathang via Sher Bagh at an estimated cost of Rs 7,610 lakh. Scheduled for completion by October next year, the bridge is expected to improve connectivity between the adjoining localities. Kundra expressed satisfaction with the progress and reiterated the need for timely execution.
Earlier, at the Government Polytechnic College, Kurbathang, the Chief Secretary reviewed the construction of a 200-seater Computer-Based Training Centre being developed at a sanctioned cost of Rs 24.66 crore. Central Public Works Department officials informed him that around 85 per cent of the physical work has been completed and the facility is expected to be handed over by November.
He also assessed the progress of academic infrastructure comprising classrooms, laboratories, a library, computer centre, common room and faculty rooms, being constructed at a cost of Rs 1,416.08 lakh, with completion targeted for August next year.
Kundra further reviewed staff residential quarters being built at a cost of Rs 670.47 lakh, directing officials to expedite the remaining work without compromising construction quality.
The Chief Secretary also visited the hostel being constructed for Children With Special Needs (CWSN) near the Council Secretariat at Kurbathang. The residential facility is being developed at a cost of Rs 489.16 lakh.