₹1,925-Cr projects to bring Grid connectivity to Siachen, Nubra and Zanskar
LEH: Three strategic power transmission projects under the Prime Minister’s Development Package (PMDP) are on course for completion by the end of September, paving the way for grid connectivity to Nubra, Zanskar and Siachen Base Camp for the first time and expanding electricity infrastructure across Ladakh’s remote border regions.
With an investment of ₹1,925 crore, the projects include a 189-km, 220 KV transmission line from Drass to Padum and a 79-km, 220 KV transmission line from Phyang to Disket, along with associated substations. Once commissioned, the projects are expected to provide uninterrupted electricity to remote settlements, reduce dependence on diesel generators and advance the Union Territory’s transition towards cleaner energy.
The projects will extend the power grid to six of Ladakh’s seven districts, leaving only Changthang outside the grid network until its proposed transmission infrastructure is completed.
The progress of the transmission projects was recently reviewed by Lieutenant Governor VK Saxena, who was briefed by senior officials of REC Limited and the Ministry of Power. The Lieutenant Governor directed implementing agencies to adhere to the September deadline and ensure coordinated execution to provide reliable electricity to remote and border areas without delay.
Officials informed the review meeting that strategically sensitive regions, including Nubra, Zanskar and Changthang, continue to rely on limited local generation, resulting in intermittent electricity supply. The ongoing transmission projects are intended to integrate these regions with the national power grid while expanding the power distribution network across the Union Territory.
Under the transmission plan, four substations will be established across Zanskar to provide electricity throughout the valley. In Nubra, substations at Siachen Base Camp and Partapur will support continuous power supply in one of India’s most sensitive border regions.
The government has also proposed eight substations under a 66 KV transmission network for Changthang at Durbuk, Phobrang, Chushul, Mudh-Nyoma, Korzok, Hanle, Koyul and Chumathang to strengthen electricity access across the high-altitude plateau.
According to the administration, reliable electricity is expected to improve healthcare, education, tourism, digital connectivity, livelihoods and local economic activity while strengthening infrastructure in frontier areas. The transmission network is also expected to enhance operational support in strategically important sectors along Ladakh’s northern frontier.
Lieutenant Governor VK Saxena said uninterrupted electricity would improve the quality of life in remote villages while creating new opportunities for economic growth and entrepreneurship. He emphasised that timely completion of the projects would strengthen infrastructure in border areas and ensure that households across Ladakh benefit from round-the-clock power supply at the earliest.