UT Ladakh tightens project handover rules, technical panel to vet works

Multi-disciplinary committee to inspect quality, safety, services and compliance before projects are handed over

YASH KHAJURIA

LEH: The Administration of the Union Territory of Ladakh has constituted a multi-disciplinary Technical Committee to physically verify, technically assess and evaluate the quality of works and projects executed by various departments before they are handed over or taken over.

The committee has been constituted with the objective of ensuring that projects are completed in accordance with approved Detailed Project Reports (DPRs), technical sanctions, drawings, specifications, prescribed quality and safety standards and other applicable codal provisions.

The Chief Engineer, PW(R&B) Department will head the committee as Chairman. Its members include the Joint Director of Hospitality & Protocol/representative of the concerned department, representatives of PHE and PDD not below the rank of Executive Engineer, a representative of the Mechanical Engineering Department, a representative of NIC Ladakh and the Divisional Fire Officer, Leh Fire & Emergency Services.

Under its terms of reference, the committee will conduct physical inspection of projects at site and compare the actual execution with the approved scope, components and provisions contained in the DPR and technical sanction. It will also verify whether sanctioned quantities, specifications, designs and other provisions have been executed by the concerned agency.

A major component of the exercise will be quality assessment, with the committee required to examine construction quality and materials used and determine whether the works conform to prescribed technical specifications, applicable standards and relevant codal provisions.

The committee will additionally inspect the completeness and functionality of essential services and installations, including electrical systems, water supply, sanitation, mechanical installations, firefighting and fire-safety arrangements, NIC/IT services and other allied works, wherever applicable.

Before recommending a project for handover, the committee will ensure that necessary testing and commissioning of services, equipment and installations have been undertaken and that relevant test certificates and reports are available.

The order also places emphasis on identifying and rectifying deficiencies. If any defect, incomplete work or non-compliance is detected during inspection, the committee will record it and specify the corrective measures required. The executing agency will then be required to rectify such shortcomings before the project can be recommended for handing/taking over.

Significantly, the committee has been mandated to categorise each project into one of three conditions: fit for handing/taking over; fit after rectification of specified deficiencies; or not fit for handing/taking over, with reasons clearly recorded.

Its recommendations will be based on both physical inspection and scrutiny of project records. Executing agencies have been directed to provide approved DPRs, technical sanctions, drawings, estimates, measurement records, quality-control reports, test certificates, commissioning reports and other relevant documents required for verification.

The committee may also seek assistance from other technical officers or experts, or co-opt subject-matter specialists where necessary, with the approval of its Chairman. The consolidated reports are to be submitted to the concerned departments within a reasonable timeframe to facilitate timely completion, commissioning and handing/taking over of projects.