Rajnath Singh virtually inaugurates Rs 3,500 crore GRSE, YIL expansion projects in WB

NEW DELHI: Defence Minister Rajnath Singh on Sunday virtually performed the Bhumi Pujan for five expansion projects of Garden Reach Shipbuilders and Engineers (GRSE) and Yantra India Limited (YIL) involving a combined investment of around ₹3,500 crore, aimed at expanding India’s shipbuilding, ship repair and indigenous defence manufacturing capacity.

The projects include three GRSE facilities at Raichak in South 24-Parganas, Shalimar in Howrah and Kidderpore in Kolkata, besides two projects at YIL’s Metal and Steel Factory (MSF), Ishapore. Singh said the expansion would strengthen India’s defence production base, reduce dependence on foreign sources and create employment opportunities for MSMEs and allied industries.

The largest of the GRSE projects is planned at Raichak, where the shipyard will invest more than ₹2,500 crore to develop a 32-acre facility with a 356-metre waterfront and an existing 96-metre jetty. The facility will be capable of constructing warships up to 200 metres long and commercial vessels of up to 60,000 deadweight tonnes.

The Raichak complex will include a 200-metre dry dock, 200-metre slipway, 200-metre ship-launching pad, two jetties, block fabrication and consolidation facilities, hull repair shops and supporting infrastructure. Singh said the facility would also enable GRSE to bid for next-generation destroyers.

At Timber Pond, Shalimar, GRSE plans to invest nearly ₹100 crore to revive a four-acre facility acquired on a 30-year lease. The project includes restoration of a 130-metre dry dock, construction of a 120-metre slipway and installation of a dry dock gate and gantry crane.

At Kidderpore, around ₹70 crore will be invested in the Damodar facility to undertake medium-sized vessel repairs and construct electric ferries and other small craft.

The two YIL projects at Ishapore involve a combined investment of more than ₹750 crore. These include a 3,000-tonne Heavy Duty Hydraulic Open Die Forging Press, which will replace the 2,650-tonne press operational since 1976, and a Radial Forging Plant costing ₹473.84 crore.

The new forging press is scheduled for completion in 26 months and will support production of gun barrels, ammunition components and heavy defence forgings. YIL estimates annual savings of ₹25.58 crore from the facility.

The Radial Forging Plant, with a 30-month execution timeline, will produce super-alloy forgings, hollow tubes for aerial bombs, components for future ordnance systems, railway axles and nuclear reactor components. The facility is projected to generate annual profit of about ₹69 crore, according to the statement.

Singh said the projects reflected the government’s push for Aatmanirbharta in defence and Make in India, Make for the World. He also highlighted India’s opportunity to expand its presence in global shipbuilding, design and ship repair.

He said India’s engineering talent, skilled workforce, steel industry and MSME ecosystem could help the country emerge as a major shipbuilding and Maintenance, Repair and Overhaul (MRO) hub.

West Bengal Chief Minister Suvendu Adhikari said the projects would expand GRSE and YIL capacities while supporting industrial activity, employment and ancillary industries in the state.